As we approach the end of the year, progress claim certifiers have two claim rounds to manage before the break, and the Christmas pause in security of payment timeframes isn’t the same everywhere.

Every Security of Payment Act (SOPA) stops its business day count over Christmas, but each state sets its own dates. Here’s when the pause starts and ends in each state for Christmas 2026, what changes in Victoria this year, and how to plan the December claim cycle before you go on leave.

This article is general information only, not legal advice. Deadlines depend on your contract, where the work is carried out and when a claim is served, so check the current legislation or get legal advice before relying on any date.

When is the security of payment Christmas shutdown for 2026?

Every state and territory’s security of payment legislation pauses its business day count over Christmas, but each sets its own dates, so the length of the pause depends on where the job is. That pause is the Christmas shutdown period: the days each state’s Security of Payment Act leaves out of its business day count over Christmas and New Year, so statutory timeframes pause. This year, Victoria joins Queensland and WA on the longest pause, at nearly three weeks.

Here’s how it falls for Christmas 2026, with two example claims: one served at the end of November, and one served the Friday before Christmas.

The December claim calendar: Christmas 2026 to January 2027
State or territory Christmas period excluded Last business day of 2026 First business day of 2027 Payment schedule due for a claim served Mon 30 Nov Payment schedule due for a claim served Fri 18 Dec
NSW 27 to 31 Dec Thu 24 Dec Mon 4 Jan Mon 14 Dec Mon 11 Jan
ACT 27 to 31 Dec Thu 24 Dec Mon 4 Jan Mon 14 Dec Mon 11 Jan
Tasmania 27 to 31 Dec Thu 24 Dec Mon 4 Jan Mon 14 Dec Mon 11 Jan
South Australia 27 to 31 Decplus any day of a statewide industry shutdown Thu 24 Dec Mon 4 Jan Mon 21 Dec Mon 18 Jan
Victoria 22 Dec to 10 Jan Mon 21 Dec Mon 11 Jan Mon 14 Dec Thu 21 Jan
Queensland 22 Dec to 10 Jan Mon 21 Dec Mon 11 Jan Mon 21 Dec Fri 29 Jan
Western Australia 22 Dec to 10 Jan25 Dec to 7 Jan for contracts under the Construction Contracts Act 2004 Mon 21 Dec Mon 11 Jan Mon 21 Dec Fri 29 Jan
Northern Territory 25 Dec to 7 Janworking days Thu 24 Dec Fri 8 Jan Notice of dispute due Mon 14 Dec Notice of dispute due Fri 15 Jan

The last two columns are examples only, calculated by Buildsoft on 20 November 2026. They assume the claim was served that day, the contract sets no shorter time, and the Act’s default period applies: 10 business days for a payment schedule in NSW, the ACT, Tasmania and Victoria, and 15 in South Australia, Queensland and WA. The Northern Territory works differently: where the contract is silent, a disputed claim needs a notice of dispute within 10 working days. The dates allow for the public holidays on 25 and 28 December, 1 January and 26 January. Christmas Eve is a part-day public holiday in South Australia from 7pm, but under SA law it still counts as a business day.

 

 

 

Why does December hold two claim cycles for progress claim certifiers?

For progress claim certifiers, most months follow a familiar rhythm. A contractor claims at the end of the month, you assess it, the payment schedule goes out, and there are a couple of weeks of breathing space before the next claim lands. December squeezes two of those rounds into one month, with the Christmas shutdown in the middle.

The first round is November’s. A contractor’s November payment claim (a progress claim made under the state’s security of payment legislation, which starts the statutory timeframes) is often served around Monday 30 November. It’s still being assessed in early December, and it needs a payment schedule: the respondent’s written reply to a payment claim, stating the amount it will pay and the reasons for paying less. On the Act’s default timeframes, that’s due Monday 14 December in NSW, Victoria, Tasmania and the ACT, and Monday 21 December in Queensland, WA and South Australia. In Queensland and WA, that’s the last business day before the Christmas shutdown.

The second round is December’s, and it can arrive earlier than usual. Many contractors want to be paid before the holidays, so a December claim may land in the week before Christmas, where the contract allows it, or while your office is closed. In Victoria, the Act now lets a claim for work done from 1 to 21 December be served from 22 December. So the December claim can land in the same fortnight you’re finishing the November payment schedule.

That’s the December claim cycle: the two claim rounds a progress claim certifier handles in December, the payment schedule for the November claim, and the December claim that arrives just before or during the Christmas shutdown period. The November round needs to be finished before you go on leave. The December round needs a plan, because its deadlines fall in January, often in the first week back.

Contracts can set earlier claim dates and shorter response times than the Act, so treat these default dates as a starting point and check each contract.

What changes in Victoria this Christmas?

Christmas 2026 is the first time Victoria’s Security of Payment Act pauses over the holidays. Until this year, Victoria was the only state without a Christmas pause, and a claim served just before the break kept its clock running through the holidays. Since 15 April 2026, Victoria’s Act has left 22 December to 10 January out of its business days. The state’s regulator, the Building and Plumbing Commission (BPC), sets out what that means in its summary of the changes to the Act, including that the excluded days also pause the adjudication deadlines.

The amended Act also sets December’s claim dates. As the BPC explains in its guide to making a payment claim, a claim for work done 1 to 21 December can be served from 22 December, and a claim for work done 22 to 31 December from 31 January the following year. A contract can allow earlier service, but not later. If you want to check the wording yourself, law firm DLA Piper’s overview of the reforms points to the sections of the Act that set these dates. That means a Victorian December claim can arrive on 22 December, inside the shutdown, and its count won’t start until business days resume on 11 January.

The reforms go well beyond Christmas, so it’s worth checking how they affect your Victorian contracts more broadly.

Does a payment claim served over Christmas still count?

It’s a familiar question in January: a claim arrived on 23 December, nobody saw it until the team was back, so does it count? Yes. A payment claim served during the Christmas shutdown period is still served. The count simply starts once business days resume.

In Queensland, the regulator spells this out each year. The Queensland Building and Construction Commission (QBCC) publishes a notice before the holiday period, and last year’s notice used the example of an invoice given on the last business day of 2025, with the count running from the first business day of 2026. The QBCC usually publishes the notice for the coming break in late November, so check its website for this year’s version.

When in the day a claim arrives matters too. In NSW, a claim served after hours on a business day counts as served that day, whatever the contract’s deemed-service clause says. The NSW Court of Appeal confirmed this in Roberts Co (NSW) v Sharvain Facades [2025] NSWCA 161, and law firm Herbert Smith Freehills Kramer’s summary of the decision explains how a claim emailed at 7.18pm on a Friday left the respondent’s payment schedule out of time. So a claim emailed at 7pm on Christmas Eve on a NSW job is served on 24 December. Its 10 business days run from Monday 4 January, putting the payment schedule due on Friday 15 January (an example only).

And a claim doesn’t have to arrive in the inbox you’re watching. As law firm Thomson Geer points out in its Christmas guide to payment claims and payment schedules, a claim can be served at your registered office or principal place of business as well as any address in the contract, so someone needs to be checking those too.

Can the contract set dates that ignore the shutdown?

A construction contract can’t give you longer than the Security of Payment Act allows, but it can give you less, and that’s what catches people out at Christmas. If the contract’s deadline for a payment schedule falls before the Act’s, the contract’s earlier deadline is the one you have to meet. If the contract counts calendar days, those days keep running through the Christmas break while the Act’s business days are paused. In Allencon v Palmgrove [2023] QCA 6, Queensland’s Court of Appeal held that a subcontract’s 21 calendar day period for a payment schedule applied over the 2021 to 2022 Christmas break, rather than the Act’s 15 business days. Law firm Pinsent Masons’ analysis of the case walks through how the calendar days ran out while the Act’s business days were paused. A contract that allows 14 calendar days to respond to a claim served on 18 December runs out on 1 January, wherever the job is, unless the contract moves deadlines that fall on a holiday to the next business day.

So before the break, check whether each contract counts calendar days or business days, and how it defines them.

Do adjudication timeframes pause over Christmas too?

When a payment claim ends up in adjudication, the Christmas shutdown period usually applies there too. Where adjudication timeframes are counted in business days, the same excluded days apply. In Victoria, the Building and Plumbing Commission’s summary of the changes to the Act confirms that the excluded days pause the strict adjudication deadlines. In Queensland, the Queensland Building and Construction Commission’s holiday period notice counts an adjudication application made over the break from the first business day after it. If a claim does go to adjudication, a clear, dated record of how you reached each assessment is what you’ll want in front of you.

How should progress claim certifiers prepare for the December claim cycle?

The December claim cycle covers two claim rounds: the payment schedules for November’s claims, and the December claims that arrive just before or during the Christmas shutdown. Most of the preparation happens before anyone goes on leave, and much of it is the kind of housekeeping that’s easy to push to “next week” until next week is Christmas. Working through these steps job by job covers both rounds:

  • List every active job by state, and note its last and first business days from the December claim calendar earlier in this article.
  • Check each contract’s claim dates, response times, day count (calendar or business days) and addresses for service.
  • Where the contract allows, agree a December claim date with each contractor, without suggesting it limits their statutory rights.
  • Name who checks claim inboxes, portals and the registered office over the break.
  • Agree with the client who will sign payment schedules while people are on leave.
  • Finish open assessments, with your reasons recorded, before leave starts.
  • Diarise the first business day back for each job.

Get those done, and January starts with a list of known dates instead of a surprise in the inbox.

Where does Notum fit?

When the team comes back in January, the first job is picking up where everyone left off: which claims are open, what was assessed, and what the contract says about the next deadline. Notum, progress claims software by Buildsoft for quantity surveyors who assess and certify claims independently on behalf of a Principal, Client or financier, keeps each project’s contract, claims and assessments in one place, so that record is ready when you are.

Vera, Notum’s AI assistant, finds and summarises contract clauses, reviews the contractor’s claim when it arrives and reviews your assessment before you certify. It reviews and reports, but doesn’t approve or certify. Over Christmas, that means Vera can find what each contract says about payment terms and timeframes, including how it counts days, with clause references. It doesn’t track statutory deadlines, so check those against your state’s Act.

Request a Demo of Notum Progress Claims software

Frequently asked questions

What is the last business day before Christmas 2026 under security of payment?

Monday 21 December in Victoria, Queensland and WA. Thursday 24 December in NSW, the ACT, South Australia, Tasmania and the Northern Territory.

When do security of payment business days restart in January 2027?

Monday 4 January in NSW, the ACT, South Australia and Tasmania. Friday 8 January in the Northern Territory, and Monday 11 January in Victoria, Queensland and WA.

Does a payment claim served on Christmas Eve still count?

Yes, it’s still served. If 24 December is a business day where the job is, the count starts from that day, and in NSW that holds even if the claim arrives after hours.

Do adjudication deadlines pause over Christmas?

Where adjudication timeframes are counted in business days, the same Christmas periods apply. Check your state’s Act and the regulator’s guidance for the detail.

 

This article sets out the Christmas periods in each state and territory’s security of payment legislation, and example dates for Christmas 2026 to January 2027, as at the last-updated date shown above. It is general information only and is not legal advice. Contracts can set shorter timeframes or count calendar days, some types of work follow different rules, and the legislation changes from time to time. Before relying on any date, check the current legislation or get advice from a qualified construction lawyer. Buildsoft does not accept liability for any loss arising from reliance on this article.

23 Nov 2026

Related Articles

Security of Payment Acts (often called SOPA) give anyone who carries out construction work, or supplies related goods and services,…